DATE

TIME

FDR/CKT

AREAS AFFECTED

PURPOSE

ESTIMATED
NUMBER OF
CONSUMERS
AFFECTED

ESTIMATED
UNDILEVERED/
UN-USED ENERGY
(KWHR)

Oct. 20, 2014
(Monday)

9:00AM-5:00PM

Feeder 1

Amsing Road - Pacdal, B.C.

BENECO POWER INTERRUPTION: 
- Re-routing of secondary lines

89

112.22

Feeder 11

Tram - Ucab, Itogon

BENECO POWER INTERRUPTION: 
- Re-routing of secondary lines

150

176.61

Rose/Jasmin Street - Monterrazas Village, Binatangan -
Tuding, Itogon

BENECO POWER INTERRUPTION: 
- Replacement of rotten primary pole

49

56.77

Feeder 9

Parts of Shilan - LTB (along Shilan-Beckel Road)

BENECO POWER INTERRUPTION: 
- Relocation of secondary pole

13

10.12

Circuit 1

Gaswiling, Sagubo, Gadang - Kapangan

BENECO POWER INTERRUPTION: 
- Replacement of rotten primary & secondary poles

711

276.69

Feeder 9

Parts of Km. 6 Betag near Bell Church, La Trinidad

BENECO POWER INTERRUPTION: 
- Uprating of 1-50kVA Communal Transformer to 100kVA

447

74.00

Feeder 10

Parts of Pico, Near Public Market, La Trinidad

BENECO POWER INTERRUPTION: 
- Replacement of 240V lines from #1/0 ACSR to
  #4/0ACSR

54

110.40

Parts of Balili, Near Puregold, La Trinidad

BENECO POWER INTERRUPTION: 
- Replacement of 240V lines from #1/0 ACSR to
  #4/0ACSR

131

333.60

Feeder 2

Parts of Upper Amistad, Camp 7, Baguio City

BENECO POWER INTERRUPTION: 
- Uprating of 1-50kVA Communal Transformer to 75kVA

127

241.60

Oct. 21, 2014
(Tuesday)

9:00AM-5:00PM

Feeder 11

Loacan - Itogon except Luneta Antamok, Ubolan, Kingstown Subdivision, Sapsing - Beckel, LTB, HEDCOR Fabrication Building

BENECO POWER INTERRUPTION: 
- Retensioning of primary lines
- Replacement of rotten primary pole

NGCP POWER INTERRUPTION: (2-Hours)
- To facilitate retrieval of one (1) 55-ft steel pole

902

904.00

Feeder 11

Alpha Ville Subdivision, Binanga Sur/Norte, Baguio Gold - Tuding, Itogon

BENECO POWER INTERRUPTION: 
- Line clearing / Tree cutting

299

281.20

Feeder 2

Major parts of Eagle Crest Phase 1, Bakakeng Norte/Sur, Baguio City

BENECO POWER INTERRUPTION: 
- Replacement of 240V lines from #1/0 ACSR to
  #4/0ACSR

121

231.20

Feeder 5

Parts of North Sanitary Camp, Near Beneco Substation

BENECO POWER INTERRUPTION: 
- Installation of additional 23kV Lines

149

141.60

Oct. 22, 2014
(Wednesday)

9:00AM-5:00PM

Feeder 8

Bakakeng Norte/Sur (Green Summerville, Richview
Subdivision, SLU-SVP Housing Old Site)

BENECO POWER INTERRUPTION: 
- Rerouting of primary lines

1,238

2,032.00

Feeder 9

Dapiting, Alapang - LTB

BENECO POWER INTERRUPTION: 
- Replacement of undersized secondary pole

155

180.87

Feeder 4

Sunnyside Fairview, Central/Upper Fairview, Upper/Lower/Middle Quezon Hill, Quezon Hill Proper, Victoria Village

BENECO HOTLINE MAINTENANCE ACTIVITIES:
- Replacement of broken primary pole

526

693.08

Feeder 8

Parts of Roseville Interior C Balacbac, Sto. Tomas Proper, Baguio City

BENECO POWER INTERRUPTION: 
- Uprating of 1-25kVA Communal Transformer to
  37.5kVA

41

100.80

Feeder 10

Parts of Buyagan, near Buyagan Elementary School, Poblacion La Trinidad

BENECO POWER INTERRUPTION: 
- Replacement of 240V lines from #2/0 ACSR to
  #4/0ACSR

60

124.80

Parts of Buyagan, near Jesus Church, Poblacion La Trinidad

BENECO POWER INTERRUPTION: 
- Replacement of 240V lines from #2/0 ACSR to
  #4/0ACSR

120

280.00

Oct. 23, 2014
(Thursday)

9:00AM-5:00PM

Dalicno Line

PMA - Baguio City

BENECO POWER INTERRUPTION: 
- Line clearing
- Rerouting of primary lines

318

1,788.11

Feeder 3

Marville Homes Subdivision, Tadiangan, Tuba

BENECO POWER INTERRUPTION:
- Replacement of rotten primary/secondary poles

49

280.00

Feeder 4

Parts of Ferguzon Road, Campo Filipino, Baguio City

BENECO POWER INTERRUPTION: 
- Extension of 3-phase 23kV Lines and Installation of
  3-10kVA Sole-use Transformers

322

560.00

Oct. 24, 2014
(Friday)

9:00AM-5:00PM

Feeder 7

Middle/East/West Quirino Hill, B.C.

BENECO POWER INTERRUPTION:  
- Relocation of primary pole

600

584.00

Feeder 3

San Carlos Heights - Irisan, Parts of San Luis Village (San Luis
Extension, Bermuda Subdivision)

BENECO POWER INTERRUPTION:
- Replacement of collapsed primary poles

11,604

16,686.00

Feeder 2

Parts of Loakan-Liwanag, Baguio City

BENECO POWER INTERRUPTION: 
- Replacement of 240V lines from #2/0 ACSR to
  #4/0ACSR

136

163.20

Luelco Line

Parts of Upper Sokiao, Camp 1, Tuba

BENECO POWER INTERRUPTION: 
- Extension of 240V #2/0 ACSR Lines for new consumers

44

108.00

Oct. 25, 2014
(Saturday)

9:00AM-5:00PM

Feeder 9

Parts of Puguis, LTB (nearby BSU Campsite-Training Farm /along Puguis-Longlong Road)

BENECO POWER INTERRUPTION: 
- Replacement of dilapidated secondary pole

42

47.66